01THE PROJECT
Timeline
OUR JOURNEY TO 2033
From project selection in 2024 to planned completion in 2033
B-CITY’s ten-year development roadmap at a glance
2023
- 09.05Call for Enterprise Innovation Park proposalsMOLIT Announcement No. 2023-1077
- 11.09Pilot project proposal submittedDouzone Bizon / Chuncheon City
- 12.07Proposal evaluation
2024
- 03.11Presidential remarks at the 19th People’s Happiness Forum
- 03.18Land Transaction Permission Zone designated by Gangwon StateGangwon State Announcement No. 2024-426
- 03.27Pilot project selection announcedMOLIT Growth Hub Policy Division, Document No. 691
- 06.12First consultation with MOLIT
- 06.27Designated a National High-Tech Strategic Industry Specialized Complex for biotechnologyChuncheon · Hongcheon
- 08.29Development Activity Permit Restriction Area designatedChuncheon City Notice No. 2024-468
- 09.09Gangwon State and Chuncheon City confirmed their PFV equity stakes
- 11.20Environmental Impact Assessment Council review
- 12.30Land Transaction Permission Zone adjustedGangwon State Announcement No. 2024-1965
2025
- 01.09Development Activity Permit Restriction Area amendedChuncheon City Notice No. 2025-14
- 04.23AMC establishedBiotech Innovalley Asset Management Co., Ltd. — asset management company
- 08.28PFV establishedBiotech Innovalley PFV Co., Ltd. — project financing vehicle
- Aug–OctConsultations with Gangwon State and Chuncheon City departments; public inspection and hearing
- NovApplication for MOLIT approval of the Integrated Development Plan
2026
- AprResidents’ briefing in Gwangpan-ri
- JulPublic hearing on the draft Integrated Development Plan
- JulFeasibility study commences
- JulLIMAC review
- AugFinal reports for the Strategic Environmental Impact Assessment and Environmental Impact Assessment submitted to MOLIT
- DecMOLIT approval of the Integrated Development Plan — planned
2027
- 1QSecure project financing (planned)
- 2QSite development works begin
2029
- 4QPhase 1 completion
2033
- 4QFull project completion
Government, local authorities and the private sector are moving B-CITY forward
on the schedule set out — without delay